Schedule

Final delivery: June 17, 2025
Each sprint lasts 14 days

Sprint Goals Deliverables Start Date End Date
SPRINT 0 - Define frontend and backend responsibilities
- Set up communication tools
- Study current repository and map existing infrastructure
- Identify initial technical dependencies
Team alignment document
Initial technical mapping
2025-03-24 2025-04-06
SPRINT 1 - Gather requirements for EcoPoints and CMS
- Analyze existing APIs and dependencies
- Start building the backlog
Requirements document
Technical dependencies report
2025-04-07 2025-04-20
SPRINT 2 - Finalize detailed requirements and acceptance criteria
- Prioritize and structure the backlog
- Start API and static map prototype
Prioritized backlog
Initial EcoPoints prototype
2025-04-21 2025-05-04
SPRINT 3 - Complete EcoPoints module (filters, location, tests)
- Start CMS with CRUD structure and user roles
Functional EcoPoints module
CMS prototype (CRUD + roles)
2025-05-05 2025-05-18
SPRINT 4 - Finalize CMS features (editing, validation)
- General testing and polish
- Draft technical and user documentation
Fully functional CMS
Initial documentation
2025-05-19 2025-06-01
SPRINT 5 - Final testing, bug fixes, stakeholder validation
- UX adjustments and official delivery
Final validated system
Final documentation
Delivery
2025-06-02 2025-06-17

πŸ“† Planned Meetings

Meeting Date Participants Purpose
Sprint 0 – Kickoff 2025-03-24 Dev Team + PM Initial alignment and technical structuring
Sprint 0 – Follow-up 2025-03-31 Dev Team + PM Review studies and stack mapping
Sprint 1 – Planning 2025-04-07 Dev Team + PM Start requirements gathering and API analysis
Sprint 1 – Follow-up 2025-04-14 Dev Team + PM Validate technical dependencies and domain understanding
Sprint 2 – Planning 2025-04-21 Dev Team + PM Consolidate backlog and start technical development
Sprint 2 – Follow-up 2025-04-28 Dev Team + PM Check progress on EcoPoints module
Sprint 3 – CMS Kickoff 2025-05-05 Dev Team + PM Review EcoPoints completion and start CMS
Sprint 3 – Follow-up 2025-05-12 Dev Team + PM Validate filters integration and CMS structure
Sprint 4 – CMS Finalization 2025-05-19 Dev Team + PM Finalize features and testing
Sprint 4 – Follow-up 2025-05-26 Dev Team + PM Review documentation and final integration
Sprint 5 – Final Delivery Check 2025-06-10 Dev Team + PM + Stakeholders Validate final product with stakeholders
Sprint 5 – Wrap-up 2025-06-17 Dev Team + PM Final presentation, delivery and retrospective

Revision History

Date Version Changes Authors
2024-03-28 0.1 Document creation CainΓ£ Freitas, Lucas Antunes
2025-04-06 0.2 Updated document with Ecolink scope and timeline Mateus Vieira
2025-04-08 0.3 Adjusted for 14-day sprints and final deadline Mateus Vieira